Project Description
This project involves upsizing the existing 6-inch sewer lines to 12-inch and 16-inch lines along SR 776 from Biscayne Drive to the Charlotte Sports Park. This is an in-kind project for the Florida Department of Environmental Protection (FDEP) Consent Order.
Project Location
Along SR 776 from Biscayne Drive to the Charlotte Sports Park.Project Impacts
Acquisition of pipe delayed project start.
The project is currently delayed. The department is in coordination with FDOT for directional drills and MOT approvals.
Latest Updates
Construction has begun along SR 776. Driveway access to various businesses may be impacted.
Budget
Phase | Cost |
---|---|
Construction | $977,737.95 |
Total Budget | $977,737.95 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 06/01/2021 | 12/15/2023 |
Project Phase
Project Complete
Last Updated
12/15/2023
Project Manager
Mike Martindell
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Construction Contractor
Stevens and Layton Inc.